Viva Energy Gas Terminal Project EES Technical Report A2
March 2022 — Southeast Australia
Client: AECOM
Appendix A-1 – Baseline Monitoring of Ambient Underwater Noise Environment
Appendix A-2 – Underwater Noise Modelling
Appendix A-3 – Underwater Noise Impact Assessment
Three underwater noise studies that form part of the Environment Effects Statement for the Viva Energy Gas Terminal Project in southeastern Australia. The project will develop a gas terminal using a floating storage and regasification unit (FSRU) moored at Refinery Pier in Corio Bay, Geelong to facilitate supply of a new source of gas for the south-east Australian gas market where there is a projected supply shortfall in coming years.